You can specify the font, background color, and row height for information displayed in a table.
Choose View, Table Font and Row.
To specify a general table font, click the Font button.
To select a background color, click the Color button.
In the Row Height area:
To use the current row heights you set, mark the Keep Current Row Heights checkbox.
To automatically size row heights based on the cell content, clear the Keep Current Row Heights checkbox and choose Optimize row heights by content. Mark the checkbox, Do not exceed X lines per row, to limit the amount of lines created by text wrapping and optimizing the row heights.
To specify a row height for all rows in the current layout, clear the Keep Current Row Heights checkbox and choose Select height for all rows. Type a new row height in the field, or click the arrow buttons.
I agree with Philip, The presentation should be in readable form(which should be our ultimate goal), what is wrong in presenting two sheets of the schedule? is there any rule saying to display all in one?.
As you position the bars, you need more row height. There is a simple solution, keep the bars in the same position and change their thickness and colours. This will give you wgat you want, but make sure the people reading the reports understand the layout.
If there is too much activity information to be shown on one A3 page then try printing to adobe acrobat, selecting "print to A2 or A1" paper size. Adobe then creates the print which you can then print to A3. The programme is scaled to suit!! The only problem is the size of the text but you can`t win them all!!
Im appreciating the comments of all, I have been gone through what u all are explain, still I have not achieved the target.
In my schedule (master Program) contain 190 activities I have to make in one A3 Size paper; I feel the only possible way is to reduce the gab between the target bar and early, I have no idea is there is any option in p3 to reduce this gap, yesterday I already posted this query to primavera knowledge base, so far I did not have any response, if any Know please,
The best way is set the Baseline bar and update bar position as one in the modify bar definition dialogue box. Make Baseline bar bigger than the update bar as appropriate, If you experience any delay in the activities that will be coming out of baseline bar(since both in the same position). This will save number of items to be displayed in one single sheet(either A3 or A4). Still if you can’t solve this problem use summary bar option to summarize activities to some reasonable level or summarize any particular group which is not of so important to your management concern and display remaining important activities as appropriate to your mgmt.
In addition to row height, change the bars, start point, end point and label sizes. You can able to show the baseline and updated bars in one page. Believe the schedule is for summary only.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
You can specify the font, background color, and row height for information displayed in a table.
To use the current row heights you set, mark the Keep Current Row Heights checkbox.
To automatically size row heights based on the cell content, clear the Keep Current Row Heights checkbox and choose Optimize row heights by content. Mark the checkbox, Do not exceed X lines per row, to limit the amount of lines created by text wrapping and optimizing the row heights.
To specify a row height for all rows in the current layout, clear the Keep Current Row Heights checkbox and choose Select height for all rows. Type a new row height in the field, or click the arrow buttons.
a) Make the row height adjustable automatically by selecting all activities
b) By adjusting the column width and remove unwanted columns, you can show your schedule with baseline and updated bar
c) Better to select page orientation in Portrait form which is best suited for your case
I agree with Philip, The presentation should be in readable form(which should be our ultimate goal), what is wrong in presenting two sheets of the schedule? is there any rule saying to display all in one?.
Hi Azvi,
As you position the bars, you need more row height. There is a simple solution, keep the bars in the same position and change their thickness and colours. This will give you wgat you want, but make sure the people reading the reports understand the layout.
Regards
Philip
If there is too much activity information to be shown on one A3 page then try printing to adobe acrobat, selecting "print to A2 or A1" paper size. Adobe then creates the print which you can then print to A3. The programme is scaled to suit!! The only problem is the size of the text but you can`t win them all!!
Regards
Graham
Im appreciating the comments of all, I have been gone through what u all are explain, still I have not achieved the target.
In my schedule (master Program) contain 190 activities I have to make in one A3 Size paper; I feel the only possible way is to reduce the gab between the target bar and early, I have no idea is there is any option in p3 to reduce this gap, yesterday I already posted this query to primavera knowledge base, so far I did not have any response, if any Know please,
Best Regard
Azvi
Azvi,
Please aware of the "position" of the baseline when you define the bar. The bigger the number the thicker each row.
Other tricks:
1) Try Portrait instead of Landscape for page orientation.
2) Reduce the height of the header and footer.
3) Do not show "Dates" to both top and bottom of the page.
4) Reduce the font size of displayed columns.
5) Reduce the font size of the "organised headings".
6) Reduce the level of "organising".
7) Reduce the top and bottom page mragin.
Clarence
Azvi,
The best way is set the Baseline bar and update bar position as one in the modify bar definition dialogue box. Make Baseline bar bigger than the update bar as appropriate, If you experience any delay in the activities that will be coming out of baseline bar(since both in the same position). This will save number of items to be displayed in one single sheet(either A3 or A4). Still if you can’t solve this problem use summary bar option to summarize activities to some reasonable level or summarize any particular group which is not of so important to your management concern and display remaining important activities as appropriate to your mgmt.
HTH
Daya
Azvi,
In addition to row height, change the bars, start point, end point and label sizes. You can able to show the baseline and updated bars in one page. Believe the schedule is for summary only.
Cheers!!!
You can increase the row height of all activities or selected activities or make it automatic size.
Can you be more specific, like you have to show everything in 1(one) A3 sheet. or it can go into no of pages. or do you need descriptions etc on bar.