Hi All,
Would like to know if we can show overlla % compelete in PRimavera updated schedule.
I have been progress measuring using excel in which some activities progress is measured by
- Manhours
- Cost
But the OVerall weightage is claulated based on the assigned weighate as per Contract for example
Engineering - 15%
Procurement - 40%
Construction - 35%
Commissioning - 10%
So can we show this in PRimavera 6 updated schedule ?
Regards
Jithin
You can create a resources for that purpose and assign cost to all activities, factored by Weighting that you have per EPCC WBS
You could use the WBS facility 'WBS Milestone % complete' in order to exactly track the EPCC percentages you quote.