Existing" resources etc - what exactly is being updated? How come all my projects bleed together for resources? - If I say "use existing" for calendar or resources - and it changed in update - won't my project not match the original import?
"Update Existing" resources etc - what exactly is being updated? How come all my projects bleed together for resources?
Forum Sponsor
Top Posters
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
Hmm. 'Bleed together for resources' - this sounds a bit like a query about all projects sharing the same pool of resources. Which is correct, and almost the whole point of an enterprise-wide project management system. You can partition the resource dictionary such that you can emulate project-specific resources.
If, on import, you chose 'use existing' then the project might not match the original exported project, calendar details, resource availability etc.