Days Due vs Days needed - what if you when you add up delays each month it is way more than needed? - So do you have to give an extension for way more days than necessary just because there was fat in schedule, or they are able to condense the work? If they will be done with a job in 20 days, do you have to give an extension for 60 days because that is what all of the delays added to? - obviously the "effect" was less than the raw numbers.
Days Due vs Days needed - what if you when you add up delays each month it is way more than needed?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Another way to phrase this: you are delayed 60 calendar days, the work gets done and it turns out it only delayed the job 50 days? Do you get a 60 or 50 day extension and why?