Greetings Planners
I am updating a baseline schedule, some of the activities that have actual start but not yet completed, their bar after the data date bar is not continous, there is a space between the data date and then the bar for the next period starts.
Is there any explanation for this.
Regards,
Muataz
it may well be ahead of the planned or baseline schedule
You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.
Hi Zoltan,
Won't changing Actual Work setting to Current Bar make it show progress beyond data date?
Jerome
here is the fix go to bars
go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar
Moutaz,
Most likely the your calendar start time is 08:00 while your data date time is 00:00
Check this blog post for details
https://www.plannersplace.com/blog/how-remove-gaps-after-data-date-primavera-p6
=jerome