Space in Bar

Greetings Planners

I am updating a baseline schedule, some of the activities that have actual start but not yet completed, their bar after the data date bar is not continous, there is a space between the data date and then the bar for the next period starts.

Is there any explanation for this.

Regards,

Muataz

S
Santosh Bhat 👤 Member for 21 years 1 month

You have retained logic running through the predecessors of that task, check the relationships have been upheld as you've enterered the actual dates.

J
Jerome Odeh 👤 Member for 22 years 4 months

Hi Zoltan,

Won't changing Actual Work setting to Current Bar make it show progress beyond data date?

Jerome

Z
Zoltan Palffy 👤 Member for 16 years 10 months

here is the fix go to bars 

go to the actual work bar and in the 3rd column (time scale) chneg this setting from Actual bar to Current bar

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts