I have a schedule with a must finish by date of 6/24/21. The early finish for the project is 6/29/21, so about 5 days behind schedule. But it is showing -170 days of total float. I am not sure where this is computing from. The imposed finish is 6/24/2021 in properties. I have never had this happen before. Is there something I should at?
All my other projects are showing correct float. It is only this one.
Thanks
Hi, Catherine. The good news is that if you need to compress your schedule by 5D, in Asta Powerproject you are using one of the very few software packages (along, notably, with Spider Project) that does the CPM computation of critical path drag that facilitates that process.
Fraternally in project management,
Steve the Bajan
Thanks Ben. Will do.
Hi Catherine,
Can you email your .pp file to [email protected] and mention the problem, and then we can see what is causing this.
Thanks,
Ben @ Powerproject