Float and dates don't nake sense

 I have a schedule with a must finish by date of 6/24/21. The early finish for the project is 6/29/21, so about 5 days behind schedule. But it is showing -170 days of total float. I am not sure where this is computing from. The imposed finish is 6/24/2021 in properties. I have never had this happen before. Is there something I should at?

All my other projects are showing correct float. It is only this one.

Thanks

S
Stephen Devaux 👤 Member for 21 years 3 months

Hi, Catherine. The good news is that if you need to compress your schedule by 5D, in Asta Powerproject you are using one of the very few software packages (along, notably, with Spider Project) that does the CPM computation of critical path drag that facilitates that process.

Fraternally in project management,

Steve the Bajan

B
Ben Taunt 👤 Member for 14 years 6 months

Hi Catherine,

Can you email your .pp file to [email protected] and mention the problem, and then we can see what is causing this.

Thanks,

Ben @ Powerproject

Featured Partner

Top Posters

Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts