I found your suggestion of bringing two projects into a single window is found to be useful for an example if we want to create links between activities in two different projects.
I guess the conclusion is that P3 and P3e are not the same applications and they will achieve things in a different way. P3 still has some feature which are not in P3e, but that is minor these days (certainly with the introduction of 5.0 next month).
Im still not sure what you want to do when youve split your screen.
To use the same features of P3. I wonder why some options available and essential in P3, are not available in P3e? I think we need to wait for the new version to get these options but can we get the answers too?
By splitting horizontally or vertically, do you mean bringing up 2 projects in separate windows ? If so, there is not a way to do this. P3e has a single document windows interface.
However, You can open multiple projects by ctrl + click on project open dialog. But they will be displayed in the same window.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Bill,
I found your suggestion of bringing two projects into a single window is found to be useful for an example if we want to create links between activities in two different projects.
Cheers!!!
Daya
I guess the conclusion is that P3 and P3e are not the same applications and they will achieve things in a different way. P3 still has some feature which are not in P3e, but that is minor these days (certainly with the introduction of 5.0 next month).
Im still not sure what you want to do when youve split your screen.
To use the same features of P3. I wonder why some options available and essential in P3, are not available in P3e? I think we need to wait for the new version to get these options but can we get the answers too?
Regards,
J. Daniel
You can split your activities view by chosing a Gantt chart (for instance) in both your top and bottom layout.
What is it that you want to achieve?
Cheers,
Niek.
J Daniel,
By splitting horizontally or vertically, do you mean bringing up 2 projects in separate windows ? If so, there is not a way to do this. P3e has a single document windows interface.
However, You can open multiple projects by ctrl + click on project open dialog. But they will be displayed in the same window.
Regards,
Bill