- I have a big problem when I making the baseline Schedule , Every Submittal for Approval the client make a new Comment ,
To Summarize the problem ,
The client need the schedule with Resource loading ( by Category And Manhour ) according to BOQ and Also The Productivity Should be same as the BOQ , and he need the S curve which I Make on Excel to Be Smooth
My Question , How I Aligned all of this together ? , I can make the schedule , and I put the resources by category according to the advise from the project manager ( 1 Foreman 2 helper 1 fitter etc… ) then when I check the resource assignment some weeks have overloaded resources and I can’t level it because the time will extend so I make it manually on resource assignment so the total resources per week not more what we plan internally and also to make the curve look smooth as requested form the client , and it take a huge amount of time , seriously it’s very Hard .
At all I done all I said previously , but the problem the client commented that the total manhour by Work class not the same as BOQ and Productivity is not the same the contractual one .
I Don’t Know how I Align all of this together , how I follow the milestone dates , and follow resources Category which our company will provide and they say it’s enough for the work , and Make the manhour as BOQ and Productivity as Contract and S Curve Smooth ?
What is the right planning Concept to follow ?
Can Anyone please Help me , May be I understood the Story Wrong .
If using P6 be reminded that P6 consider an even daily distribution for resource leveling therefore your leveling might still be overallocated.
If using Spider Project the software can automatically level for variable quantities taking into consideration how production rates might change.
by deafult the resource distribution is a linear function menaing it spreads the budgeted amout over the activity evenly
what you can do is assign a resource curve to the activity or create your own curve to tell it how you want to distribute the resources over the duration front loaded, back loaded, triangular
go to the activit then to the resource tab at the bottom
right click and select customize resource columns and expand the General category and select curves
from there you will see a list of different curves select the one that you want and assign that curve ot that activity.
Please be reminded that billings should cover costs of idle resources and these hidden costs must be tracked and managed as not to loose money.
Sometimes the Comments have a lot of meaning because it depends on the interpretations of every reader.
Can you provide the texts of the comments?
Sometimes the Comments have a lot of meaning because it depends on the interpretations of every reader.
Can you provide the texts of the comments?