Actual Labor Units Should Not be Budgeted Labor Units If Performance is not as per baseline

Hi experts,

 

After I enter actual progress (by changing remaining duration), I also want to change actual or remaining Labor Budgeted Units.  I know by default they also change in proportion to Duration % but may be resource has worked less or more so I would want to change it. I can change it, no problem.

 

But the problem is this that when i will mark the activity as 'Finished', the Actual Labor Budgeted Units will always change back and equivalent to Budgeted Labor Units. Software should rather calculate remaining/actual labor units as per past labor unit performance I entered i.e at activity finish, they should be less or more than Budgeted.

 

So, is there a way to let software do not make actual labor units = budgeted labor units but rather calulate remaining/actual as according to last performance.

 

Thansk

Z
Zoltan Palffy 👤 Member for 16 years 11 months

open your project 

go to the PROJECTS directory 

click on the calclations tab make dure that Recalculate Actual Units and costs when duration % complete changes is NOT checked

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts