Hello everyone.

I have problem with getting a NAN and INF in my Revised Baseline.

Scenario is this:

1. Baseline has actuals and loaded with Resources

Prior to getting the NAN (Total Float) and INF (Original Duration), all resource curve are in dafault but when I change some Resource Curve (i.e. Front Loaded), I get this NAN and INF.

Does anyone know how to solve it? Is changing the resource curve will cause this?

  

[[wysiwyg_imageupload:7343:]]

Z
Zoltan Palffy 👤 Member for 16 years 11 months

WRONG 100% WRONG !

budgeted units will NOT chnage if duration is changed (if i change to fixed duration & units/time).  

hence the word FIXED DURATION & UNITS/time

W
Warren Sika 👤 Member for 13 years 4 months

Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time).  Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

change the duration type to fixed duration & units/time. You can add a column for duration type do the first one then doa fill down

also in the PROJECTS directory under the Resources tab uncheck drive activity dates by default

Forum Sponsor

Top Posters

Trian Asmoro
1 posts
Soheil Barekat
4 posts
Erkan Polater
9 posts
Luis Jr Ngade
6 posts
Ben Welsher
1 posts
Rohan Dashputre
0 posts
AMECHI ANAKWENZE
2 posts
Jayaprakash Sekar
1 posts
arash.karmand
0 posts
James Williams
74 posts