Hello everyone.
I have problem with getting a NAN and INF in my Revised Baseline.
Scenario is this:
1. Baseline has actuals and loaded with Resources
Prior to getting the NAN (Total Float) and INF (Original Duration), all resource curve are in dafault but when I change some Resource Curve (i.e. Front Loaded), I get this NAN and INF.
Does anyone know how to solve it? Is changing the resource curve will cause this?
[[wysiwyg_imageupload:7343:]]
WRONG 100% WRONG !
budgeted units will NOT chnage if duration is changed (if i change to fixed duration & units/time).
hence the word FIXED DURATION & UNITS/time
Thank you Engr. Zoltan. Unfortunately, I dont want to mess my other data as this will cause changes to budgeted units whenever duration is changed (if i change to fixed duration & units/time). Is there any other way? I guess keeping the resource curve to default will help. I don't know if I am correct. Appreciate your help.
change the duration type to fixed duration & units/time. You can add a column for duration type do the first one then doa fill down
also in the PROJECTS directory under the Resources tab uncheck drive activity dates by default