Fire Proofing for Cables - Schedule

K
Kiran Nath 👤 Member for 9 years 4 months

Dear All,

I would like to develop a Schedule for Cable Fire Proofing incl. trays (Intumescent FireProofing cable coating)

Please let me know,

1. What kind of actvities involved in this particlualr work ?

2. What are the Constrains to be started this work ?

Please support me in this regards.....

Z
Zoltan Palffy 👤 Member for 17 years

1st you will need to survey the existing conditions to determine which cables that you want to fire proof

2nd you will have to prepare the immediate area around the cables that you want to fireproof doing things such as putting plastic on other items that you do not want to get the fire-proofing on.

3rd if possible install ventilation in the area where the fire-proofing is beiing performed

4th you will need to rope of the area where the fire-proofing is being sprayed on.   

5th Spraying of the cables is next

6th you will have to clean up any remnants of the fire-proofing that did not adhear

7th remove the plastic that you previously installed

8th remove the ventilation that you previously installed

9th remove the barrier, rope or tape from the area that you previously quarended off

10th done

Featured Partner

Top Posters

yerukalapudi
1 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts
James Williams
75 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts

Our Partners