Manpower report

R
Ron Beechey 👤 Member for 10 years 2 months

Is there a method in P6 that I have missed to see by manpower count " task to fix it " takes 2 millwrights.   I can see the budgetted manhours but I was asked if I could (like in MSP) if I could indicate the number of trades people assigned to a task.   Have I just missed something.

R
Ron Beechey 👤 Member for 10 years 2 months

Thanks Tom looks like that will work for what we are doing.   Already well into the project and have made a productivity adjudtment ( lowering from 1 to .5 by adjusting durations ) so I'mnot sure how that effect the labour hours but we will see.

T
Tom Boyle 👤 Member for 19 years 6 months

Ron,

There may be better ways, but I've used the "Calculate Average" option for the Usage profiles and spreadsheets - with "Base on Hours per Time Period" checked.  The corresponding unit of measure that I use is "LEM" for "labor equivalent men."

Good luck, tom

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts