Is there a method in P6 that I have missed to see by manpower count " task to fix it " takes 2 millwrights. I can see the budgetted manhours but I was asked if I could (like in MSP) if I could indicate the number of trades people assigned to a task. Have I just missed something.
Ron
I do the same thing that Tom does
Thanks Tom looks like that will work for what we are doing. Already well into the project and have made a productivity adjudtment ( lowering from 1 to .5 by adjusting durations ) so I'mnot sure how that effect the labour hours but we will see.
Ron,
There may be better ways, but I've used the "Calculate Average" option for the Usage profiles and spreadsheets - with "Base on Hours per Time Period" checked. The corresponding unit of measure that I use is "LEM" for "labor equivalent men."
Good luck, tom