High Rise Building Schedule

hi there 

is there any one share some of his best experience for high rise building project schedule any pdf or XER will really help 

or can you please give list of activities for one typical floor with or without duration 

you can send me the info as email on [email protected]

thanks in Advanced 

M
masyitah sunbae 👤 Member for 9 years 1 month

hye...anyone can help me..i need example activity shedulling that high rise building such condominium or apartment in 4 block and duration 3 year...please help me..

R
Raymund de Laza 👤 Member for 16 years 6 months
  Activity Name Original Duration
  Design and Engineering 51
  Design Building Addition 23
  Design 43
  Review and Approve Designs 9
  Assemble Technical Data for Heat Pump 3
  Review Technical Data on Heat Pumps 8
  Procurement 132
  Prepare and Solicit Bids for Heat Pump 10
  Review Bids 10
  Prepare and Solicit Bids for Flooring 5
  Review Bids for Heat Pump 2
  Review Bids for Flooring 3
  Award Contract for Heat Pump 10
  Review Bids for Brick 3
  Award Contract for Flooring 1
  Award Contract for Brick 2
  Fabricate and Deliver Flooring 58
  Deliver Brick 58
  Fabricate and Deliver Heat Pump and Controls 88
  Sitework   114
  Site work I 50
  Sitework 95
  Site work II 45
  Foundation 79
  Foundation 64
    Excavation 24
  Begin Building Construction 0
  Excavation 10
    Form Work 12
  Install Underground Water Lines 5
  Install Storm water lines 10
    Concrete 79
  Site Preparation 10
  Form/Pour Concrete Footings 10
  Concrete Foundation Walls 14
  Form and Pour Slab 10
  Backfill and Compact Walls 5
  Foundation Phase Complete 0
  Structure   172
  Structure 143
  Erect Structural Frame 40
  Begin Structural Phase 0
  Floor Decking 28
  Concrete First Floor 60
  Erect Stairwell and Elevator Walls 10
  Concrete Basement Slab 15
  Concrete Second Floor 15
  Mechanical/Electrical Systems 133
  Rough-In Phase Begins 0
  Rough In Complete 0
  Elevator   165
  Elevator 138
  Install Elevator Rails and Equipment 40
  Install Elevator Cab and Finishes 20
  Plumbing and Electrical 181
  Set Mechanical and Electrical Equipment 15
  Electrical Costs 152
  Rough-In Plumbing/Piping 45
  Install Wiring and Cable 45
  Connect Equipment 3
  HVAC   186
  HVAC, Plumbing & Fire Protection 155
  Install HVAC Ducts 25
  Insulate Ducts 2
  Set Heat Pump 5
  Relocate HVAC Chiller 3
  Startup and Test HVAC 1
  Install AC Grills and Registers 5
  Test and Balance HVAC Equipment 1
  Exterior Finishes 278
  Exterior Finish Costs 205
    Brick   266
  Assemble Brick Samples 3
  Review and Approve Brick Samples 10
  Brick Exterior Walls 14
    Roof   10
  Insulation and Built-up Roofing 10
    Doors and Windows 3
  Install Door and Window Frames 1
  Install Exterior Doors and Windows 2
  Interior Finishes 373
  Drywall in Offices 15
  Interior Finish Costs 44
  Finishes Phase Begins 0
  Finishes Milestone 0
  Touch-up and Clean-up 1
  Building Addition Complete 0
  Punch List 2
    Plumbing and Lighting Fixtures 17
  Install Lighting Fixtures 3
  Install Plumbing Fixtures 2
    Floor and Carpeting 362
  Assemble and Submit Flooring Samples 8
  Review and Approve Flooring 10
  Install Floor and Carpeting 5
    Carpentry 30
  Install Ceiling Grid 15
  Finish Carpentry and Millwork 5
    Paint   36
  Paint Building Interior 30
J
John Peter 👤 Member for 15 years 2 months

Muhammad you are absolutely right this forum is made to help all planners in our community.

People like Gary don’t understand this. Most of the planners  who write that sort of comments spend most of their office time on internet and rest of the time doing some design plans for desktop surveys.

 If you don’t have any knowledge how do you share something!!! But can give loads of lame excuses.

I hope this example help you. Most people in this forum share their experience because they have knowledge

 

Activity Name Original Duration Remaining Duration Start Finish Total Float
City Center Office Building Addition 681 554 01-Nov-10 A 3-Jul-13 0
  Design and Engineering 107 0 01-Nov-10 A 06-Apr-11 A  
    Design Building Addition 55 0 01-Nov-10 A 19-Jan-11 A  
    Start Office Building Addition Project 0 0 01-Nov-10 A    
    Review and Approve Designs 22 0 17-Jan-11 A 17-Feb-11 A  
    Assemble Technical Data for Heat Pump 7 0 16-Feb-11 A 25-Feb-11 A  
    Review Technical Data on Heat Pumps 27 0 24-Feb-11 A 06-Apr-11 A  
  Foundation 146 98 23-Feb-11 A 19-Sep-11 175
    Begin Building Construction 0 0 28-Feb-11 A    
    Site Preparation 43 0 23-Feb-11 A 18-Apr-11 A  
    Excavation 24 24 2-May-11 6-Jun-11 127
    Install Underground Water Lines 12 12 3-Jun-11 21-Jun-11 127
    Install Underground Electric Conduit 12 12 3-Jun-11 21-Jun-11 127
    Form/Pour Concrete Footings 24 24 21-Jun-11 26-Jul-11 127
    Concrete Foundation Walls 24 24 25-Jul-11 26-Aug-11 127
    Form and Pour Slab 12 12 26-Aug-11 14-Sep-11 127
    Backfill and Compact Walls 5 5 13-Sep-11 19-Sep-11 127
    Foundation Phase Complete 0 0   19-Sep-11 178
  Structure 151 151 19-Sep-11 20-Apr-12 306
    Erect Structural Frame 48 48 19-Sep-11 25-Nov-11 127
    Begin Structural Phase 0 0 25-Nov-11   418
    Floor Decking 34 34 25-Nov-11 13-Jan-12 127
    Concrete First Floor 36 36 11-Jan-12 1-Mar-12 127
    Erect Stairwell and Elevator Walls 24 24 1-Mar-12 4-Apr-12 139
    Concrete Basement Slab 24 24 1-Mar-12 4-Apr-12 139
    Concrete Second Floor 36 36 1-Mar-12 20-Apr-12 127
    Structure Complete 0 0   20-Apr-12 127
  Mechanical/Electrical Systems 562 549 14-Apr-11 A 26-Jun-13 0
    Rough-In Phase Begins 0 0 12-Mar-12   234
    Rough In Complete 0 0   5-Feb-13 0
    Elevator 218 218 4-Apr-12 12-Feb-13 90
      Install Elevator Rails and Equipment 3 3 4-Apr-12 6-Apr-12 217
      Install Elevator Cab and Finishes 5 5 5-Feb-13 12-Feb-13 91
    HVAC 562 549 14-Apr-11 A 26-Jun-13 0
      Prepare and Solicit Bids for Heat Pump 15 2 14-Apr-11 A 4-May-11 0
      Review Bids for Heat Pump 10 10 4-May-11 17-May-11 0
      Award Contract for Heat Pump 6 6 17-May-11 25-May-11 0
      Fabricate and Deliver Heat Pump and Controls 422 422 25-May-11 23-Jan-13 0
      Install HVAC Ducts 24 24 12-Mar-12 13-Apr-12 186
      Insulate Ducts 5 5 18-Jun-12 25-Jun-12 140
      Set Heat Pump 12 12 4-Jan-13 22-Jan-13 0
      Relocate HVAC Chiller 7 7 22-Jan-13 1-Feb-13 0
      Startup and Test HVAC 2 2 1-Feb-13 5-Feb-13 0
      Install AC Grills and Registers 5 5 8-Apr-13 15-Apr-13 23
      Test and Balance HVAC Equipment 2 2 21-Jun-13 26-Jun-13 0
    Plumbing and Electrical 258 258 20-Jan-12 23-Jan-13 6
      Set Mechanical and Electrical Equipment 36 36 20-Jan-12 12-Mar-12 186
      Rough-In Plumbing/Piping 3 3 24-Aug-12 29-Aug-12 72
      Install Wiring and Cable 36 36 31-Aug-12 23-Oct-12 72
      Connect Equipment 1 1 22-Jan-13 23-Jan-13 6
  Exterior Finishes 336 289 17-Feb-11 A 19-Jun-12 266
    Close-In Phase Begins 0 0 15-May-12   296
    Building Enclosed 0 0   18-Jun-12 127
    Brick 312 265 17-Feb-11 A 15-May-12 124
      Assemble Brick Samples 0 0 17-Feb-11 A    
      Review and Approve Brick Samples 30 0 28-Feb-11 A 13-Apr-11 A  
      Prepare and Solicit Bids for Brick Exterior 15 0 18-Mar-11 A 13-Apr-11 A  
      Review Bids for Brick 15 0 08-Apr-11 A 28-Apr-11 A  
      Award Contract for Brick 5 4 21-Apr-11 A 5-May-11 377
      Deliver Brick 1 1 5-May-11 6-May-11 377
      Brick Exterior Walls 17 17 20-Apr-12 15-May-12 127
    Roof 24 24 15-May-12 19-Jun-12 124
      Insulation and Built-up Roofing 24 24 15-May-12 19-Jun-12 127
    Doors and Windows 7 7 27-Apr-12 8-May-12 152
      Install Door and Window Frames 3 3 27-Apr-12 1-May-12 156
      Install Exterior Doors and Windows 5 5 1-May-12 8-May-12 156
  Interior Finishes 601 554 25-Feb-11 A 3-Jul-13 0
    Drywall in Offices 36 36 5-Feb-13 27-Mar-13 0
    Touch-up and Clean-up 2 2 19-Jun-13 24-Jun-13 0
    Finishes Complete 0 0   26-Jun-13 0
    Punch List 5 5 26-Jun-13 3-Jul-13 0
    Building Addition Complete 0 0   3-Jul-13 0
    Plumbing and Lighting Fixtures 44 44 8-Apr-13 10-Jun-13 7
      Install Lighting Fixtures 7 7 8-Apr-13 17-Apr-13 21
      Install Plumbing Fixtures 5 5 3-Jun-13 10-Jun-13 7
    Floor and Carpeting 581 534 25-Feb-11 A 4-Jun-13 0
      Assemble and Submit Flooring Samples 0 0 25-Feb-11 A    
      Review and Approve Flooring 28 0 25-Feb-11 A 11-Apr-11 A  
      Prepare and Solicit Bids for Flooring 24 5 04-Apr-11 A 6-May-11 231
      Review Bids for Flooring 15 15 6-May-11 27-May-11 231
      Award Contract for Flooring 5 5 27-May-11 6-Jun-11 231
      Fabricate and Deliver Flooring 279 279 3-Jun-11 6-Jul-12 231
      Install Floor and Carpeting 12 12 16-May-13 4-Jun-13 0
    Carpentry 59 59 27-Mar-13 19-Jun-13 0
      Install Ceiling Grid 36 36 27-Mar-13 16-May-13 0
      Finish Carpentry and Millwork 12 12 3-Jun-13 19-Jun-13 0
    Paint 12 12 14-Feb-13 4-Mar-13 76
      Paint Building Interior 12 12 14-Feb-13 4-Mar-13 77
M
Muhammad Zeeshan Khan 👤 Member for 18 years 2 months

Gary its a shame that people dont help each other i am not ask for the programme i am just asking for the list of activities 

List of activities does not belongs to any programme and it is always good to share your experience and best practices you have used.

Those who not share are mostly P6 jockey and I appreciate and salute all those project professional who are helping planning community without thinking about doesn't know how to do their job to stay in a job which they don't deserve,feel it is giving away their experience for free" they all are mean little buggers and they should not be on this forum 

Cheers

M
Muhammad Zeeshan Khan 👤 Member for 18 years 2 months

Well i am looking for simple high rise building used as an office upto 20th floor have a curtain wall .

I need some list of Mechanical, Electrical and Plumbing activities 

G
Gary Whitehead 👤 Member for 17 years 2 months

Muhammad,

 

Most people on this forum don't share their programmes.

I personally never do, because I feel the programmes I create are the property of my client, and not mine to share.

Other people never do becuase they feel it is giving away their experience for free, when they normally charge for it.

Others don't because they feel it is helping someone who doesn't know how to do their job to stay in a job which they don't deserve.

Some people do share their work but not many, so don't be annoyed or suprised if you don't get what you are looking for.

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

There are high rise building such as Water Tank Tower with a revolving Restaurant on Top, Guard House Tower Building around a perimeter fence of a Military Compound, Tower buildings such as in Dubai.

The list of activities depends on what is required by the Contract Project.

 

Regards,

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts