MSP: Elapsed total float ignored - even when increasing threshold for critical tasks

H
Henrik I 👤 Member for 7 years 9 months

Please see attached. What is going on here? Bug?

msp.png

Many thanks 

Kind regards,

Henrik

H
Henrik I 👤 Member for 7 years 9 months

Many thanks Tom! Brilliant :-)

I should have thought of that.

T
Tom Boyle 👤 Member for 19 years 6 months

No bugs.

  1. Assuming you've left the project's "hours per day" at the default value of 8, then your critical slack threshold of 6 days is 6x8=48 hours.
  2. On the two tasks selected, the Total Slack is 2.63 elapsed days x 24 hours per elapsed day = 63.12 hours.
  3. Since 63.12 > 48, the two tasks are not Critical.
  4. For these tasks to show as Critical, you would need to increase the critical threshold from 6 days to 8 days (i.e. 64 hours).

In this case, your true Critical Path might be difficult to discern without tracing the driving logic.

Good luck, tom 

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts