MSP: Elapsed total float ignored - even when increasing threshold for critical tasks

H
Henrik I 👤 Member for 7 years 10 months

Please see attached. What is going on here? Bug?

msp.png

Many thanks 

Kind regards,

Henrik

H
Henrik I 👤 Member for 7 years 10 months

Many thanks Tom! Brilliant :-)

I should have thought of that.

T
Tom Boyle 👤 Member for 19 years 7 months

No bugs.

  1. Assuming you've left the project's "hours per day" at the default value of 8, then your critical slack threshold of 6 days is 6x8=48 hours.
  2. On the two tasks selected, the Total Slack is 2.63 elapsed days x 24 hours per elapsed day = 63.12 hours.
  3. Since 63.12 > 48, the two tasks are not Critical.
  4. For these tasks to show as Critical, you would need to increase the critical threshold from 6 days to 8 days (i.e. 64 hours).

In this case, your true Critical Path might be difficult to discern without tracing the driving logic.

Good luck, tom 

 

 

Featured Partner

Top Posters

James Williams
75 posts
Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners