how to display Planned Vs Baseline curves w.r.t time?

Member for

16 years 3 months

1st you wil need to assign resources to the baseline schedule

next copy the baseline schedule and use the copy to do your updating 

then you can compare the baseline vs the current

Member for

13 years 11 months

Thanx i will try to do this and if i feel any difficulty then i will get back to you.

best regards,

kk

Member for

14 years 9 months

Hi Kashif

Planned and Baseline is same, you might be trying to compare %progress timewise planned/baseline vs actual

you can do one thing,

1)     Define a resource nonlabor type (i.e. Dur ) keep price/unit as 0 and default unit/time and max unit/time as 1 

so for any activity budgeted units is same as duration (i.e. 1* duration = duration).
2)     Select all activity by pressing Ctrl+A (highlight all) Resource from the menu.
3)     Select the new created resource (i.e. Dur ) and double click. (These will assign resource to all highlighted activities)

4) now go to reports Activity Resource and Role Assignments  , see monthly/weekly and cummulative budgeted units for this resource (Dur), now u can plot these weekly/monthly values in excel to get the  S-curve for planned duration complete.

5) once u update the schedule same way u can get the actual budgeted units for resource (Dur), and plot this against the planned curve.

this is just to compare duration complete planned vs actual   
 

regards

Mudasir

Member for

15 years 11 months

Hi,

Baseline = Planned... what you will compare?