Planned and Baseline is same, you might be trying to compare %progress timewise planned/baseline vs actual
you can do one thing,
1) Define a resource nonlabor type (i.e. Dur) keep price/unit as 0 and default unit/time and max unit/time as 1
so for any activity budgeted units is same as duration (i.e. 1* duration = duration). 2) Select all activity by pressing Ctrl+A (highlight all) Resource from the menu. 3) Select the new created resource (i.e. Dur) and double click. (These will assign resource to all highlighted activities)
4) now go to reports Activity Resource and Role Assignments , see monthly/weekly and cummulative budgeted units for this resource (Dur), now u can plot these weekly/monthly values in excel to get the S-curve for planned duration complete.
5) once u update the schedule same way u can get the actual budgeted units for resource (Dur), and plot this against the planned curve.
this is just to compare duration complete planned vs actual
Member for
16 years 3 months1st you wil need to assign
1st you wil need to assign resources to the baseline schedule
next copy the baseline schedule and use the copy to do your updating
then you can compare the baseline vs the current
Member for
9 years 2 monthsHope this
Hope this helps
https://youtu.be/cocNGNW9nOY
Member for
13 years 11 monthsThanx i will try to do this
Thanx i will try to do this and if i feel any difficulty then i will get back to you.
best regards,
kk
Member for
14 years 9 monthsHi Kashif Planned and
Hi Kashif
Planned and Baseline is same, you might be trying to compare %progress timewise planned/baseline vs actual
you can do one thing,
1) Define a resource nonlabor type (i.e. Dur ) keep price/unit as 0 and default unit/time and max unit/time as 1
so for any activity budgeted units is same as duration (i.e. 1* duration = duration).
2) Select all activity by pressing Ctrl+A (highlight all) Resource from the menu.
3) Select the new created resource (i.e. Dur ) and double click. (These will assign resource to all highlighted activities)
4) now go to reports Activity Resource and Role Assignments , see monthly/weekly and cummulative budgeted units for this resource (Dur), now u can plot these weekly/monthly values in excel to get the S-curve for planned duration complete.
5) once u update the schedule same way u can get the actual budgeted units for resource (Dur), and plot this against the planned curve.
this is just to compare duration complete planned vs actual
regards
Mudasir
Member for
13 years 11 monthsthe %age progress, manhour,
the %age progress, manhour, cost
Member for
15 years 11 monthsHi, Baseline = Planned...
Hi,
Baseline = Planned... what you will compare?