Hello all - My layout has the column 'BL Project Physical % Complete', however it appears P6 won't allow me to export this column as it doesn't show up as an option in the columns when exporting. With our reporting it would be very useful to show the previous/baseline physical % complete compared to the current physical % complete.
Does anyone know how to export the 'BL Project Physical % Complete' column into excel?
Thanks ahead of time.
ANYTHING that if you can display as a column you can export to excel
display the column
select all of your data (edit selat all)
right click and select export to excel
done
...... any why will "Schedule % compete" not do instead? It is baseline-based.......