Hello all - My layout has the column 'BL Project Physical % Complete', however it appears P6 won't allow me to export this column as it doesn't show up as an option in the columns when exporting. With our reporting it would be very useful to show the previous/baseline physical % complete compared to the current physical % complete.

Does anyone know how to export the 'BL Project Physical % Complete' column into excel?

Thanks ahead of time.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

ANYTHING that if you can display as a column you can export to excel

display the column 

select all of your data (edit selat all) 

right click and select export to excel

done 

D
David Kelly 👤 Member for 21 years 7 months

...... any why will "Schedule % compete" not do instead? It is baseline-based.......

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts