Schedule% complete & Performance % complete is not appearing

A
adab azeez 👤 Member for 9 years 10 months

Greetings to all.
I am updating a project in primavera.I need to present schedule % and performance % in the WBS of activities. But it is always showing zero, though the activity sch.% and performance% are rolling up with the update.
Need a guidance.

Thanks in advance.

A
adab azeez 👤 Member for 9 years 10 months

Thank you Mr. Zoltan.
If resource unit per price is not zero then % progress will roll up with every status update. I have done it.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

create an activity for that particular wbs and give it the activity TYPE of wbs summary then it will roll up and summarize that particular wbs for you. You can not roll up the wbs in the way that you are doing it becasue activities can use different wats to mecasure their progress you can use duration % complete, physical % complete or units % complete. So if you tried to summarize them by youe would be mixing applles and oranges and bananas. The soultion is to use WBS summary.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts