Hi,
I am analysing a program for a dispute. The dispute occured part way through the project so the delays are retrospective but the impact is prospective.
My client, I beleive by accident changed a calendar for a future few activities from a 24x7 to a 8hr/day calendar. Effectively slipping the program by a sizeable chunk of time. Can this calendar be corrected back to 24x7 for an arbitration? will the arbitrator accept such a major correction?
Thanks,
Regards,
Vijay
Hi V
Are you acting as an expert witness in an arbitration?
If so you need to be aware of the special requirements needed for such a position.
The question that you have just asked indicates that you do not fully understand your role.
Best regards
Mike T.
Hi V
A flawed baseline programme can be rectified provided the analysts explains why it i necessary.
The opposition will challenge the correction and the arbitrator will then decide which is preferable.
Best regards
Mike T.