Correcting Program for Delay analysis

V
V Kutty 👤 Member for 15 years 4 months

Hi,

I am analysing a program for a dispute. The dispute occured part way through the project so the delays are retrospective but the impact is prospective.

My client, I beleive by accident changed a calendar for a future few activities from a 24x7 to a 8hr/day calendar. Effectively slipping the program by a sizeable chunk of time. Can this calendar be corrected back to 24x7 for an arbitration? will the arbitrator accept such a major correction?

Thanks,

Regards,

Vijay

M
Mike Testro 👤 Member for 20 years 5 months

Hi V

Are you acting as an expert witness in an arbitration?

If so you need to be aware of the special requirements needed for such a position.

The question that you have just asked indicates that you do not fully understand your role.

Best regards

Mike T.

M
Mike Testro 👤 Member for 20 years 5 months

Hi V

A flawed baseline programme can be rectified provided the analysts explains why it i necessary.

The opposition will challenge the correction and the arbitrator will then decide which is preferable.

Best regards

Mike T.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts