Hi Everyone,
Can anyone please help in providing solution for above Event Code in P6?
The above event code occured with I was Maintaining Baseline., Could not do any further assignment. Please help.
Thanks in advance.
Vinit
Hi Everyone,
Can anyone please help in providing solution for above Event Code in P6?
The above event code occured with I was Maintaining Baseline., Could not do any further assignment. Please help.
Thanks in advance.
Vinit
it appears that you ahve reached your 4 gb limit. This issue can be caused when you have reached the maximum database limit. The database limit with SQL Server Express 2005 is 4 GB
You can shirnk the database and the file and you can deleted some of your older projects. Before you delete them make xer files so you can access them later if need be.
to shrink the database
Go to Start Programs Microsoft SQL server 2005, SQL Management Express Studio
the sever name is the name of the computer \Primavera
Authentication is SQL Server Authentication
User name is sa
password is Prima123Vera then click connect
Expand the databases highlight pmdb$primavera
rigth click and select Task
then shrink
then database