Hi,
I need help in understanding how to upload a primavera xer file into FUSE for the DCMA14 check with an attached baseline. The problem I am getting is, FUSE is showing baseline dates which are totally different to my attached baseline dates in the xer schedule.
I have assigned the baseline to both current project and also the same baseline to the primary baseline but FUSE refuses to pick these dates.
Any help will be appreciated.
Thanks
I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system. It's what I do to check for changes from one to the other. I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.
Hope that helps.
Thom
I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system. It's what I do to check for changes from one to the other. I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.
Hope that helps.
Thom