Hello,
What is the easiest and quickest way of exporting from P6 to MSP without dates and hours looking mental? I've tried doing a straightforward export but a lot of my dates have changed, even for completed activites, and the work is also incorrect?
Any help would be appreciated.
Thanks
The only safe way to do it is to use Collabro's Legare software.
ah.. thanks. Tried that yesterday, dates were all over the place.
Looks like I'll need to check the dates of 2000 activities line by line
Thanks anyway
sorry I meant XML
Hi Zoltan,
Can you explain the html method?
Thanks
try the html method
does not matter what you do they will never match the way msp handlesa wbsis different, calendars are different, the alogrithm calculation for the forward and backward pass is different, the way MSp handles milestone is different. Just be glad that you do noy have to type the activities again