Updating over 7000 Activities in p6

Hello Everyone,

I'v created baseling schedule contains over 7000 activities. I have to update them now by activity % complete. Is there and fast way to update them by excel if I have the data already in excel?

Z
Zoltan Palffy 👤 Member for 17 years

yes export the activites to excel you will need to export the actual start field, actual finish field and either the remaining duration and or the duration % complete.

Progress 2 activities manually in P6 progress one that has started but has not yet finished and progress another one that has started AND finished use to see the format that is expected for the input data.

The actual start TIME and the actual finish TMES must be included in the import. 

Featured Partner

Top Posters

Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts