- if you do, then budgeted costs will be computed based on your budgeted quantities * unit price... an not the other way around.
- if you want your cost budgets to be independent of your budget quantities, then create a resource (Examlple: BUDGET) and load each and every activity with this resource and put a price per activity accordingly. You can use a spreadsheet to import/export the data. The total should equal your contract price. In this case, you may experience large variances when you monitor because you are being forced to cost your activities based on budget and not based on resources required to accomplish activities.
The difference in perspectives between P3 (which does bottom-up budgeting) and your director (who wants top-down budgeting) may be better addressed by P3e (which does top-down budgeting).
Also, I think that if you already have budgets per activity, then your estimating team should have had developed a materials take-off, which should have been the basis of your budget. If so, then you could just grab a hold of this, do some tweaking in a spreadsheet, and distribute this across activities in P3.
You need to go through P3 601, 602 and 603 courses. These courses are empowering!
Your request is very unusual, but in the case of having deferent distribution curves for resource unit and cost, you should assign a dummy cost resource for each real resource and then set “Unit Price = 0” in all real resources and set real Unit Price for dummy ones. In this case you will have two resources assigned per each real resource in the activities. So you can define front loaded curve for real resources and back loaded curve for dummy cost resources.
I have a similar question with my previous one: how to tell P3 to develop cost curve that is independent to resource curve.
For example, when I input or create a linear resource loading, P3 also develops a linear cost loading. Is it possible for P3 to develop a back loaded cost based on a front loaded resource?
if i clear check box at autocost rules, p3 will recalculate cost manually but it still not solve the problem
for example
my director adjusted in one of activity (from the group of activies) only has 1000 USD bugdeted. he ask me how many resourses that needed and how far duration to finished it ?
should i do trial and errors to reach the bugdet ?
thx
you can go to auto cost rules then clear check box which is describe link between BC and BQ
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Decide if you want quantities linked to costs.
- if you do, then budgeted costs will be computed based on your budgeted quantities * unit price... an not the other way around.
- if you want your cost budgets to be independent of your budget quantities, then create a resource (Examlple: BUDGET) and load each and every activity with this resource and put a price per activity accordingly. You can use a spreadsheet to import/export the data. The total should equal your contract price. In this case, you may experience large variances when you monitor because you are being forced to cost your activities based on budget and not based on resources required to accomplish activities.
The difference in perspectives between P3 (which does bottom-up budgeting) and your director (who wants top-down budgeting) may be better addressed by P3e (which does top-down budgeting).
Also, I think that if you already have budgets per activity, then your estimating team should have had developed a materials take-off, which should have been the basis of your budget. If so, then you could just grab a hold of this, do some tweaking in a spreadsheet, and distribute this across activities in P3.
You need to go through P3 601, 602 and 603 courses. These courses are empowering!
Goodluck.
Jorge
Crown Systems
Dear bambang,
Your request is very unusual, but in the case of having deferent distribution curves for resource unit and cost, you should assign a dummy cost resource for each real resource and then set “Unit Price = 0” in all real resources and set real Unit Price for dummy ones. In this case you will have two resources assigned per each real resource in the activities. So you can define front loaded curve for real resources and back loaded curve for dummy cost resources.
Regards,
Ali Vessali
Dear specialist,
I have a similar question with my previous one: how to tell P3 to develop cost curve that is independent to resource curve.
For example, when I input or create a linear resource loading, P3 also develops a linear cost loading. Is it possible for P3 to develop a back loaded cost based on a front loaded resource?
thanks
Dear Soheil Jafari,
thanks for your comment
if i clear check box at autocost rules, p3 will recalculate cost manually but it still not solve the problem
for example
my director adjusted in one of activity (from the group of activies) only has 1000 USD bugdeted. he ask me how many resourses that needed and how far duration to finished it ?
should i do trial and errors to reach the bugdet ?
thx
you can go to auto cost rules then clear check box which is describe link between BC and BQ
good luck
hi
you can go to auto cost rules then clear check box which is describe link between BC and BQ
good luck