An sterisk on start or finish date

 

Hi All,

 

What does an asterisk shown on start or finish date of an activity mean??

I understood that this symbols comes up when the activity has a constraints date (any kind).

I have received an schedule with asteriks on start or finish dates without any constraints.

Appreciate any input,

Have a nice easter days,

Carmen

C
Carmen Arape 👤 Member for 21 years 11 months

Zoltan,

Thanks, dank u well, gracias.

That is the explanation... I am using the Construction schedule and contractor is building the CM commissioning schedule and making links...

REgards

 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

There another possibility 

there is an external constraint meaning that this activity has a predecesor from a DIFFERENT PROJECT.  

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts