Hi All,
What does an asterisk shown on start or finish date of an activity mean??
I understood that this symbols comes up when the activity has a constraints date (any kind).
I have received an schedule with asteriks on start or finish dates without any constraints.
Appreciate any input,
Have a nice easter days,
Carmen
glad I could help
Zoltan,
Thanks, dank u well, gracias.
That is the explanation... I am using the Construction schedule and contractor is building the CM commissioning schedule and making links...
REgards
There another possibility
there is an external constraint meaning that this activity has a predecesor from a DIFFERENT PROJECT.