Hi
Need your support here.
This is related to Manufacturing planning works.
Activity A (Machining operation) - 15 days
Activity B (Machining operation) - 10 days
Activity C (Machining operation) - 20 days
Activity D (Machining operation) - 25 days
Activity E (Machining operation) - 5 days
Activity F (Machining operation) - 5 days.
All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).
Thanks in advance
Ram
no
Rama,
Primavera has no mechanism for automatically assigning resources.
This is called Skill Scheduling.
I also expect that your resources may have different production rates and that you would like to use norms and measure your works in physical units, etc.
If you need this functionaity try Spider Project.