Particular Resource assignment automatically in Primavera among the group of Resources

Hi

Need your support here.

This is related to Manufacturing planning works.

Activity A (Machining operation) - 15 days

Activity B (Machining operation) - 10 days

Activity C (Machining operation) - 20 days

Activity D (Machining operation) - 25 days

Activity E (Machining operation) - 5 days

Activity F (Machining operation) -  5 days.

 

All above activities were independent. We are having two resources say LATHE 1 and LATHE 2. Is is possible in Primavera , assigning a resource (either LATHE 1 or LATHE 2) automatically based on the resource availability to get better results (Shortest Project duration).

 

Thanks in advance

Ram

D
David Kelly 👤 Member for 21 years 7 months

Rama,

 

Primavera has no mechanism for automatically assigning resources. 

V
Vladimir Liberzon 👤 Member for 25 years 4 months

This is called Skill Scheduling.

I also expect that your resources may have different production rates and that you would like to use norms and measure your works in physical units, etc.

If you need this functionaity try Spider Project.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts