When I Import my Cost Loaded Schedule from One Computer to another the Cost from Project Reduces..
Cost for Many activities goes missing.
But the main computer in which the Cost Loading was done, If I import it again on the same computer Cost comes correct
that should work
Budgeted Total cost goes missing.
I will try using the add new resource setting.
which costs are we talking about budgeted, actual, actual at completion which one ?
also check your filter make sure that it is set to ALL
also go to Projects directory make sure you project is highlighted
got to the calculations tab
on the right under the Resource Assignments make sure that Add actual to remaining is checked.
also during the import process make sure that in the Update Project Options that select modify
under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new
under the Data Type Global: make sure that the action item under resources is set to insert new