Impacting delay activites in to the Programme

Hi,

What is the correct method for linking a delay activity to the baseline programme?

Two colleagues have provided the following differing information.

1. The delay activity is linked to the predecessing / successing activity of the original planned activity.

2. The delay activity is linked to the same planned activity in the baseline programme.

Some clarity would be much appreciated.

Jonthan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Jonathan - Welcome to Planning Planet.

A delay event is set into the bar chart as a single bar or a sub chart - I never use the word "fragnet".

The end of the event is then linked FS to the impacted task or tasks in the bar chart. That is all you need to know.

Whether you use the agreed baseline or an updated progressed programme depends on many factors which a skilled delay analyst would know instinctively.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts