How to calculate expected finish date in MS Project ?

K
Karthik abi 👤 Member for 9 years 11 months

Task nameBASELINE STARTBASELINE FINISHACTUAL STARTACTUAL FINISHEXPECTED COMPLETION DATEInitial01-Aug05-Aug01-Aug05-AugNATask208-Aug10-Aug08-Aug12-AugNATask311-Aug12-AugNANA16-AugTask415-Aug17-AugNANA19-AugFinal18-Aug19-AugNANA23-Aug

Task-2 exceeded 2 days, so final task is expected to be complete on 23-Aug as shown above.

How to calculate automatically the expected completion date when the actual finish date is different from baseline finish ?

P
Philip Day 👤 Member for 10 years

Karthik abi,

 

If you have linked your tasks, MSP will complete this by operating a Forwards Pass. and the final task will automatically finish on the calculated Expected Completion Date. Be sure to Auto-Schedule your tasks to achieve this.

You can check the scheduling method used on your project in the "Status" column:

Image result for msp auto schedule icon

 

You can check that the Forwards Pass is going to work correctly by checking the links in the "Precedessors" Column.

 

I hope this helps, come back to us if you need any further help.

 

Phil

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts