Task nameBASELINE STARTBASELINE FINISHACTUAL STARTACTUAL FINISHEXPECTED COMPLETION DATEInitial01-Aug05-Aug01-Aug05-AugNATask208-Aug10-Aug08-Aug12-AugNATask311-Aug12-AugNANA16-AugTask415-Aug17-AugNANA19-AugFinal18-Aug19-AugNANA23-Aug
Task-2 exceeded 2 days, so final task is expected to be complete on 23-Aug as shown above.
How to calculate automatically the expected completion date when the actual finish date is different from baseline finish ?
Karthik abi,
If you have linked your tasks, MSP will complete this by operating a Forwards Pass. and the final task will automatically finish on the calculated Expected Completion Date. Be sure to Auto-Schedule your tasks to achieve this.
You can check the scheduling method used on your project in the "Status" column:
You can check that the Forwards Pass is going to work correctly by checking the links in the "Precedessors" Column.
I hope this helps, come back to us if you need any further help.
Phil