The two fields, Planned versus Early dates, will be different if you are resource leveling and have the correct setting. Then Planned will have the resource-leveled dates and Early will have the CPM dates.
The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.
what current value the start date will take if it s not yet started.ist the Early start or the Late start?
The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.
The FINISH DATE, as well is the completion date of the activity. Ste to the finish planned date till the activity is in the future, the remaining finish date till the activity is under progress, then the actual.
regards,
Luca
PS
In P3ec have been introduced the planned date, that may be user input with the aim to have another baseline.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Yes, if you resource level the data will be from the leveling.
At difference from P3 3.1 these data will not change after a re-scheduling with the same data date.
The two fields, Planned versus Early dates, will be different if you are resource leveling and have the correct setting. Then Planned will have the resource-leveled dates and Early will have the CPM dates.
Raj I am agree with you in a CPM calculation.
Here we were discussing what P3e is showing in some fields.
The earliest dates is teh answer.
Cheers,
Luca
It will be early start & early finish if you are planning forward pass. In backward planning it will be late start and late finish.
The early date for both.
Luca
your answer:
The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.
what current value the start date will take if it s not yet started.ist the Early start or the Late start?
and same question about FINISH DATE
thanks luca for your support.
Ali
========================================
Hi
The START DATE, as per P3ec definition is the current start date of the activity. Set to the planned start date until the activity is not started, then to the actual.
The FINISH DATE, as well is the completion date of the activity. Ste to the finish planned date till the activity is in the future, the remaining finish date till the activity is under progress, then the actual.
regards,
Luca
PS
In P3ec have been introduced the planned date, that may be user input with the aim to have another baseline.