Hai to all,
please help me anybody, how to create a piping project having scope (200000 IM and 19000 ID) IN PRIMAVERA P6.
MANI
Hai to all,
please help me anybody, how to create a piping project having scope (200000 IM and 19000 ID) IN PRIMAVERA P6.
MANI
very hard to do without knowing the scope
install pipe rack structure level 1
install pipe rack structure level 2
install pipe rack structure level 3
Lay large bore piping rack level 3
Lay Small bore piping in rack level 3
Weld or Connect large bore pipe in rack level 3
Test large bore pipe in rack level 3
Insulate large bore pipe in rack level 3
Weld or Connect small bore pipe in rack level 3
Test small bore pipe in rack level 3
Insulate small bore pipe in rack level 3
Lay large bore piping rack level 2
Lay Small bore piping in rack level 2
Weld or Connect large bore pipe in rack level 2
Test large bore pipe in rack level 2
Insulate large bore pipe in rack level 2
Weld or Connect small bore pipe in rack level 2
Test small bore pipe in rack level 2
Insulate small bore pipe in rack level 2
Lay large bore piping rack level 1
Lay Small bore piping in rack level 1
Weld or Connect large bore pipe in rack level 1
Test large bore pipe in rack level 1
Insulate large bore pipe in rack level 1
Weld or Connect small bore pipe in rack level 1
Test small bore pipe in rack level 1
Insulate small bore pipe in rack level 1
Commissioning of Piping Systems
hai zoltan,
Thanks for your sugission. presently iam working on ag piping but i am not using p6,we are using only excel.
i want to use p6 for planning but i am confusing to define wbs and activities. in my project we have scope
of 354000 IM,34000 ID,600 ISO drawings,24 no.of service pipelines with different sizes and 1 rack(having 126 no.of civil grids with 3 tairs of elevation).please help me to define wbs and activities.
mani...
-------------
define scope
create wbs structure
create activites
assign logic
assign duration
assign activiites to wbs
create a resource
assign resoure to activities
assign units (manhours) and costs $(dollars) to each resource for each activity
f9 calculate schedule
done