PROBLEM WITH LEVEL 1 ROLL UP

Dear Colleague,

Please i have a problem with my programme with 550days duration on level 1 Roll up. After 8months of update i notice that the roll up duration on the level 1 is reduced by 7days now(543days) . I got confused because the same calender is in use since day 1 the update started 8 months ago

Please i need help from my noble colleague how to resolve this issue.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar.

J
Jerome Odeh 👤 Member for 22 years 4 months

Rasheed,

Is your Finish Date the same date as it was 8 months ago? 

=jerome

R
Rasheed Ajirotutu 👤 Member for 12 years 1 month

Thanks you Ronald but the same default Calender was in use from the begining of the update.

Do you have any other reason i may consider for this change.

Hoping to hear from you soon

R
Ronald Weaver 👤 Member for 23 years 2 months

I believe the summary bar duration is calculted using the Default Calendar. I would start there.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts