Please i have a problem with my programme with 550days duration on level 1 Roll up. After 8months of update i notice that the roll up duration on the level 1 is reduced by 7days now(543days) . I got confused because the same calender is in use since day 1 the update started 8 months ago
Please i need help from my noble colleague how to resolve this issue.
2 thngs you are either 7 days ahead of schedule or any new activities were added using a different calendar.
Rasheed,
Is your Finish Date the same date as it was 8 months ago?
=jerome
The default Calendar shall be the same Calendar assigned to all Acyivities.
Thanks you Ronald but the same default Calender was in use from the begining of the update.
Do you have any other reason i may consider for this change.
Hoping to hear from you soon
I believe the summary bar duration is calculted using the Default Calendar. I would start there.