What is the Impact on your schedule if the scope the client has deleted is taken away.
Do you finish on time. If Yes why are you trying to claim extension of time.
If No Why not is this due to the a client decision.
You only need to show the relevant information from a schedule point of view.
If you feel you are going to do a Loss of profit claim this has nothing to do with the schedule remember this is a commercial Issue. And should be treated in that manner.
now the client insists,the impact on the program due to this deletion should be able to recover the delays, as so far our first submission for the approval was done in nov04 and since last 4 months the client was sleeping on this issue and did not grant any approval, eventhough there were periodic reminders throug meetings and letters for the consequencetial repurcurssions in delayed decision,
my question is how to tackle this situation and highlight this issue in the program as i have already showing the delay impact with a total -ve float of 92 days as of 31.3.05, do i delete this activity from the program or do i show a suspended period of no action from the client or is there a better way to show my case ?
Your starting point is always the contract. (which is a legal document)Your client can add to, omit from or vary the works as he wishes, however in doing so he may incur additional costs and or time claims from yourselves. Starting point:
1. What does the contract state regarding deletion of the works and reduction in value?
2. What does the contract state regarding late supply of information?
3. What are the actual time implications regarding the late supply of design information?
4. What are the actual time implications regarding the deletion of the works?
5. What are the other implications regarding the deletion of the works? eg was the furniture already ordered, being manufactured, etc.
When you have an answer to the above questions, which I imagine will all be generally in your favour, you can form the basis of an entitlement to claim additional money and or time.
it all under as per the contract and as per the FIDIC and UAE law,hope you got the clear understanding and as per ur intrepetation of being legal questions i belive its all contractual which is beign asked nothing legal about it, however our legal consultants will also work w.r.t contract.
You are asking legal rather than programming questions. Have you considered the legal aspects of your claim? If you have, what is the opinion of your legal consultants?
Are you claimimg under the contract?
If not, what is the basis for your claim? common law?
As per the Contract, What is the governing law?
I think you have to sort out the legal issues first, and then start worrying about programming (and possibly also qs).
thanks for your quick response and i was intending to receive reply from you,thanks again.
with regards to claim we shall be pursuing for both EOT and financial settlement, my concern here is the EOT as you are aware that the reduction in scope has negated the impact that already had caused to the project completion by deletion of the said equipments n furniture,n the client is of the view that since these items are deleted and therefore your chances for any EOT are minimized, the furniture and equipment are mostly free standing and some special ones have some foundation and platforms to be constructed, my request is to get some clarifications of similar situations occured for other planners, how to pursue this.
i am working on the following grounds for the claim.
1loss of oppurtunity
2loss of time and effort to pursue and source these special equipments and loss of reputation of our company in the international market and i am expecting my suppliers to claim against us.
3reduction in scope by more than 20%
4 adjustment to the performence bond value and insurance etc...
I am not sure which Philip, you are asking the question, as there are a lot of them on the site. But with a 20% reduction in scope, normally, anything more than 12 to 15% depending on the spesific contract, the contractor would be entitled to remeasure and re-price the contract, and as such, re-scheduling, should also be done, taking into account the delays in issueing of the design, and reduction in scope.
It is not clear whether the furniture you refer to is free-standing, or built in. This obviously will have an effect.
Also are you claiming EOT, Financial Compensation or both?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Waseem
What is the Impact on your schedule if the scope the client has deleted is taken away.
Do you finish on time. If Yes why are you trying to claim extension of time.
If No Why not is this due to the a client decision.
You only need to show the relevant information from a schedule point of view.
If you feel you are going to do a Loss of profit claim this has nothing to do with the schedule remember this is a commercial Issue. And should be treated in that manner.
I hope this helps
thanks Andrew,
now the client insists,the impact on the program due to this deletion should be able to recover the delays, as so far our first submission for the approval was done in nov04 and since last 4 months the client was sleeping on this issue and did not grant any approval, eventhough there were periodic reminders throug meetings and letters for the consequencetial repurcurssions in delayed decision,
my question is how to tackle this situation and highlight this issue in the program as i have already showing the delay impact with a total -ve float of 92 days as of 31.3.05, do i delete this activity from the program or do i show a suspended period of no action from the client or is there a better way to show my case ?
all pprs requested to share thier experience,
regards
waseem
Waseem,
Your starting point is always the contract. (which is a legal document)Your client can add to, omit from or vary the works as he wishes, however in doing so he may incur additional costs and or time claims from yourselves. Starting point:
1. What does the contract state regarding deletion of the works and reduction in value?
2. What does the contract state regarding late supply of information?
3. What are the actual time implications regarding the late supply of design information?
4. What are the actual time implications regarding the deletion of the works?
5. What are the other implications regarding the deletion of the works? eg was the furniture already ordered, being manufactured, etc.
When you have an answer to the above questions, which I imagine will all be generally in your favour, you can form the basis of an entitlement to claim additional money and or time.
thanks uri,
it all under as per the contract and as per the FIDIC and UAE law,hope you got the clear understanding and as per ur intrepetation of being legal questions i belive its all contractual which is beign asked nothing legal about it, however our legal consultants will also work w.r.t contract.
hope it helps to help me.
thanks to all pprs
waseem
Waseem,
You are asking legal rather than programming questions. Have you considered the legal aspects of your claim? If you have, what is the opinion of your legal consultants?
Are you claimimg under the contract?
If not, what is the basis for your claim? common law?
As per the Contract, What is the governing law?
I think you have to sort out the legal issues first, and then start worrying about programming (and possibly also qs).
hi philip jonker,
thanks for your quick response and i was intending to receive reply from you,thanks again.
with regards to claim we shall be pursuing for both EOT and financial settlement, my concern here is the EOT as you are aware that the reduction in scope has negated the impact that already had caused to the project completion by deletion of the said equipments n furniture,n the client is of the view that since these items are deleted and therefore your chances for any EOT are minimized, the furniture and equipment are mostly free standing and some special ones have some foundation and platforms to be constructed, my request is to get some clarifications of similar situations occured for other planners, how to pursue this.
i am working on the following grounds for the claim.
1loss of oppurtunity
2loss of time and effort to pursue and source these special equipments and loss of reputation of our company in the international market and i am expecting my suppliers to claim against us.
3reduction in scope by more than 20%
4 adjustment to the performence bond value and insurance etc...
Hi Waseem,
I am not sure which Philip, you are asking the question, as there are a lot of them on the site. But with a 20% reduction in scope, normally, anything more than 12 to 15% depending on the spesific contract, the contractor would be entitled to remeasure and re-price the contract, and as such, re-scheduling, should also be done, taking into account the delays in issueing of the design, and reduction in scope.
It is not clear whether the furniture you refer to is free-standing, or built in. This obviously will have an effect.
Also are you claiming EOT, Financial Compensation or both?