Hello Gents/Ladies,
When you are on Contractor side when can you allowed to change the planned %. As on a Contractor side you would issue a planning package which comes with a S curve which says that that at this week you would complete this much % of progress (Planning package - Schedule , S Curve , Weightage, narrative etc) for which you need clients approval which would be then used as a reporting basis weekly / monthly.
Can you change the Planned % as you like (contractor) or to change the planned % you need clients approval which you would only get if a deviation in the inital scope is proven.
Thanks
Jithin
You are Welcome Jithin...
Thanks Ray,
Thats the answer i was looking for and the same thing is what i followed from the start. I just needed a confirmation of what i did was correct. Thank you very much.
Hi,
You can only change when there is instruction from the Client to submit a Revised Baseline Schedule due to Changes & Modifications.
Regards,
Thanks Ray,
But can you change the Planned % without clients approval from the first planned % which was submitted (S curve) and approved by client. Are we (Contractor) authorised to change the planned % without clients approval.
Thanks
JK
HI,
The Contractor is solely in Control of the Program such as the Activities sequencing, Costs, durations, etc, therefore the Planned % shall be according to Contractors ability to execute the Schedule.