Revised Planned Percentage

Hello Gents/Ladies,

 

When you are on Contractor side when can you allowed to change the planned %. As on a Contractor side you would issue a planning package which comes with a S curve which says that that at this week you would complete this much % of progress (Planning package - Schedule , S Curve , Weightage, narrative etc) for which you need clients approval which would be then used as a reporting basis weekly  / monthly.

Can you change the Planned % as you like (contractor) or to change the planned % you need clients approval which you would only get if a deviation in the inital scope is proven.

 

Thanks

Jithin

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Thanks Ray,

Thats the answer i was looking for and the same thing is what i followed from the start. I just needed a confirmation of what i did was correct. Thank you very much.  

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi,

You can only change when there is instruction from the Client to submit a Revised Baseline Schedule due to Changes & Modifications.

Regards,

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Thanks Ray,

But can you change the Planned % without clients approval from the first planned % which was submitted (S curve) and approved by client. Are we (Contractor) authorised to change the planned % without clients approval.

 

Item Baseline Planned % Actual Completed %
Engineering    
Procurement    
Construction    

Thanks

JK

R
Raymund de Laza 👤 Member for 16 years 6 months

HI,

The Contractor is solely in Control of the Program such as the Activities sequencing, Costs, durations, etc, therefore the Planned % shall be according to Contractors ability to execute the Schedule.

 

Regards,

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts