Planned / Actual % Complete S-Curve

R
Ryan Wheal 👤 Member for 11 years 9 months

Morning all,

 

Just trying to do a very basic planned vs actual percent complete S-Curve.



Any idea how it's done?

 

I just want to show the variations between the two.



Kind regards.

R
Ryan Wheal 👤 Member for 11 years 9 months

I don't want  to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.

M
Mike Testro 👤 Member for 20 years 7 months

Hi Ryan

This is too big a topic for exchange here.

Go to Help and search on Histograms.

Select "Introduction to Histograms" and start from there.

Best regards

Mike Testro

R
Ryan Wheal 👤 Member for 11 years 9 months

Hi Mike,

 

Thanks for your response, but I'm struggling a little here.



Any chance you can help me with a walkthrough of what I'm meant to do?

 

This is the first histogram I've ever done and haven't a clue...



Kind regards,



Ryan

M
Mike Testro 👤 Member for 20 years 7 months

Hi Ryan

Asta software will do this for you.

Create a histogram with the selected data.

Right click the histogram and select S-Curve - the graph will be created in Excell.

Best regards

Mike Testro

Featured Partner

Top Posters

Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts
dagogo dan - jumbo
2 posts
Alex Lyaschenko
27 posts