Just trying to do a very basic planned vs actual percent complete S-Curve.
Any idea how it's done?
I just want to show the variations between the two.
Kind regards.
Morning all,
Just trying to do a very basic planned vs actual percent complete S-Curve.
Any idea how it's done?
I just want to show the variations between the two.
Kind regards.
I don't want to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.
Hi Ryan
This is too big a topic for exchange here.
Go to Help and search on Histograms.
Select "Introduction to Histograms" and start from there.
Best regards
Mike Testro
Hi Mike,
Thanks for your response, but I'm struggling a little here.
Any chance you can help me with a walkthrough of what I'm meant to do?
This is the first histogram I've ever done and haven't a clue...
Kind regards,
Ryan
Hi Ryan
Asta software will do this for you.
Create a histogram with the selected data.
Right click the histogram and select S-Curve - the graph will be created in Excell.
Best regards