A reflection is a copy of an active project that contains a link to the original project. It is almost the same as copy Project but reflection allows you to make changes to the reflection and then merge selected changes back into to the original project, keeping active project data such as timesheet information intact.
This is new function of Primavera allows multiple users to update reflection copy and merge it back to master schedule and allow planners to view the changes and incorporate only the changes that the planners wanted to. This functions is good to multiple user working offline in different station and make their own update.
A reflection is a copy of a project that has the following characteristics:
-> Has the same name as the original source project with reflection appended to it.
-> Internally, contains a link to the source project that allows the application to merge changes to the reflection into the source project.
-> Has a what-if status.
After creating a reflection, you can make changes to it. If desired, you can then merge selected changes back into the source project keeping active data in the source project intact. Creating a reflection facilitates the following work flows and processes:
-> Creating a sandbox area to test different project scenarios.
-> Reviewing changes made by team members to activities they own in a reflection. Using the reflection as an intermediary project lets you review and accept changes before merging the reflection back into the source project.
-> Reviewing changes to a project by exporting a reflection as an .XER file. You can send the .XER file to outside users who can import the file into their database. After making changes to the project, the outside users can export the file and send the resulting .XER file back to you. By importing the .XER file back into your reflection, you can decide which changes to keep when you merge the reflection back into the source project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
That was very usefull
Thanks
Check also these websites:
http://tensix.com/2011/11/oracle-primavera-p6-%E2%80%93-what-is-a-refle…
http://tensix.com/2011/11/oracle-primavera-p6-r8-1-reflecting-on-reflec…
Regards,
Ahmed Aziz
I personally havent used reflections that much.
Does anyone know how reliable they are in terms of merging the changes correctly?
Is it more reliable than the update baseline function?
Rodel's description is excellent. If you'd like to learn more about how to use reflections, you can view this tutorial I recently put together. https://www.planacademy.com/use-reflections-primavera-p6-to-merge-scenarios/ Hope it helps shed some light on the topic.
M
Haresh,
A reflection is a copy of an active project that contains a link to the original project. It is almost the same as copy Project but reflection allows you to make changes to the reflection and then merge selected changes back into to the original project, keeping active project data such as timesheet information intact.
This is new function of Primavera allows multiple users to update reflection copy and merge it back to master schedule and allow planners to view the changes and incorporate only the changes that the planners wanted to. This functions is good to multiple user working offline in different station and make their own update.
A reflection is a copy of a project that has the following characteristics:
-> Has the same name as the original source project with reflection appended to it.
-> Internally, contains a link to the source project that allows the application to merge changes to the reflection into the source project.
-> Has a what-if status.
After creating a reflection, you can make changes to it. If desired, you can then merge selected changes back into the source project keeping active data in the source project intact. Creating a reflection facilitates the following work flows and processes:
-> Creating a sandbox area to test different project scenarios.
-> Reviewing changes made by team members to activities they own in a reflection. Using the reflection as an intermediary project lets you review and accept changes before merging the reflection back into the source project.
-> Reviewing changes to a project by exporting a reflection as an .XER file. You can send the .XER file to outside users who can import the file into their database. After making changes to the project, the outside users can export the file and send the resulting .XER file back to you. By importing the .XER file back into your reflection, you can decide which changes to keep when you merge the reflection back into the source project.
Best Regards,
Rodel