Hi All,
The situation for EOT as follows;
There is a delay in the hand over of site to the Contractor, but as a part of mitigation the Contractor started the setting out works ahead of the official site handover- Can the Employer deduct the time of Setting Out from the delay analysis?
Regards
Kannan
Hi Mike,
Thanks for reply
Best Regards,
Sunil.
Hi Mike,
Thanks for reply
Best Regards,
Sunil.
Hi Sunil
Just set it at 100% complete and the logic will disappear.
Best regards
Mike Testro
Hi Kannan ,
If you linked finish start from the site handover to that activity, how will you update the progress in the baseline programme ?
If you update the progress that will be out of logic and how will it impact on the programme?
Best Regards,
Sunil.
Thanks for the reply...Mike
Hi Kannan
Yes.
Best regards
Mike Testro