Delay in site handover to Contractor

K
Kannan CP 👤 Member for 17 years 11 months

Hi All,

The situation for EOT as follows;

There is a delay in the hand over of site to the Contractor, but as a part of mitigation the Contractor started the setting out works ahead of the official site handover-     Can the Employer deduct the time of Setting Out from the delay analysis?

 

Regards

Kannan

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sunil

Just set it at 100% complete and the logic will disappear.

Best regards

Mike Testro

S
Sunil Babu 👤 Member for 15 years 6 months

Hi Kannan ,

If you linked finish start from the site handover to that activity, how will you update the progress in the baseline  programme ?

If you update the progress that will be out of logic and how will it impact on the programme?

 

Best Regards,

Sunil.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts